Click on the link below, which will open in a new window and shows proposed design by the architect.
Architect's Design
You will be aware that for some time that the front of the Church has required a great deal of repair and renovation. This has taken some time to come to fruition due to various aspects, from investigating the degree of the problem, to agreeing a design, an invitation to tender and obtaining planning permission from East Renfrewshire Council.
Everything has now been agreed and you will be aware that work has started.
A graphic representation of the design can be found on this page.
(You will need Adobe Acrobat Reader or something similar to view the PDF file.)
There will be a degree of inconvenience to parishioners over a period of time and we would ask you to understand this and work with us until completion.
In the short term entrance and exit to the Church will be via the side door due to safety issues and we would ask you to take care when exiting the Church at the end of Mass and show consideration to fellow parishioners, especially the elderly and disabled.
It is anticipated that any inconvenience will be kept to a minimum,
The Church organ will be out of commission for a period of time as access is required to remove some of the stained glass windows. A temporary organ will be in place during this time.
It is anticipated that the Church Stall will remain open, but there may be times when the Stall may not be available due to safety concerns. If so alternative arrangements will be made. Mass cards etc will always be available.
The work encompasses: -
A schedule of work is detailed below and will be updated on a regular basis as work progresses. (Last updated 14th October 2017)
Dates are subject to change due to inclement weather or if further problems are encountered.
Church Renovation Target Dates: -
Estimated Completion Date | ||
1 | New steelwork completed | Friday 20th October |
2 | Replacement internal Timber Screen Framework to receive stained glass | Friday 27th October |
3 | Replacement stained glass panels section adjacent to the organ pipework | Friday 27th October |
4 | Start of external curtain walling beginning of November | Thursday 30th November |
5 | Clear choir loft area | Friday 1st December |
6 | Clear main entrance | Friday 1st December |
7 | Reinstate overall use of Church for Christmas ministry | Friday 1st December |
8 | Stained Glass re-fitted start January 2018. Use of choir loft not affected | June 2018 |